Holtec predicts cost savings from building its first small modular reactors at the existing Palisades nuclear power plant ...
Less than two weeks after President Trump signed a series of executive orders intended to “usher in a nuclear energy ...
The nation's largest public power company, the Tennessee Valley Authority, announced Tuesday it submitted a construction permit application to the U.S. Nuclear Regulatory Commission for a small, ...
The first small modular reactor at the Clinch River Nuclear Site could cost around $5.4 billion, according to a draft of TVA's long-term energy plan, though the price is anticipated to decrease ...
The NRC has already said the Clinch River site is suitable for a new nuclear plant. There’s enough room for a total of four small reactors. If the NRC and the TVA board approve the plans to ...
The utility said this is the next step in bringing a small modular reactor to the Clinch River site near Oak Ridge. The application is for GE Vernova Hitachi Nuclear Energy's small modular reactor ...
It wants to develop next-generation nuclear power in Oak Ridge, Tennessee, at its Clinch River site. TVA President and CEO Don Moul said that by going first, they can show other utilities a way to ...
The Department of Energy has proposed several nuclear sites for rapid construction of power generation and data centers but ...
The NRC is expecting a complete application from the Tennessee Valley Authority for a construction permit to allow TVA to build a BWRX-300 small modular reactor (SMR) at the Clinch River Nuclear Site ...